Project development support, design, contract preparation and bid comparison for the implementation of 70 MW wind energy projects in the Rhône Valley, at Fos-sur-Mer for CN'Air.
2004 - 2006
France
Off-shore wind farm
Design of a huge off-shore wind park for C-Power off the Belgian coast on the Thornton bank. 60 wind turbines with a capacity ranging from 3,6 to 5 MW will generate over 700 GWh per year. This is the annual consumption of 180,000 families. 37 km long 150 kV connection to the belgian network.
2004 - 2007
Belgium
Lages Biomass Plant
Owner's Engineering mission for Tractebel Energia for the construction of a wood waste fired 28 MW - 120 tonnes/hour steam biomass plant.
2004 - 2004
Brazil
Energie Masterplan UZ Gasthuisberg
Energie Masterplan for the UZ Gasthuisberg Hospital complex. Long term strategic options for the energy supply, heat & cold, on-site renewable energy, cogeneration & energy efficiency, environmental constraints and reliability objectives.
2005 - 2006
Belgium
Biomass co-combustion
Design, EPC contract preparation & negotiation, technical assistance for construction & commissioning of a biomass co-combustion in the existing 70 MW coal-fired power plant of Electrabel at Rodenhuize.
2003 - 2005
Belgium
12 MW Wind farm
Project development, preliminary and basic design, wind resource assessment, tender preparation and bid comparison, construction management and O&M support to the client, Electrabel for the construction of a 12 MW wind farm at Hoogstraten.